Picture a quote that reads “concrete slab, 100 mm, supply and pour”. It is short, it has a number in it, and it sounds like everything you need to know. Most of us would nod and sign.
There is more to say than that line, and the building code says a good deal of it. This post is about a slab for a shed, a garage, a patio or a house, and it leads with the code’s own numbers on curing and steel cover and with the inspection before the pour. The inspection table covers Victoria and Queensland only, because those are the two states whose regulations we could pin down. Elsewhere, ask the building certifier. This is general information, not engineering advice.
Our position is a plain one. For a slab the code governs, the written numbers are about the concrete, the curing, the steel cover and the pour temperature. Thickness is not one of them as a single written number: the code’s slab drawings carry dimensions for slabs inside its limits, and everything else comes from a design, based on what the slab carries and what the ground is like. And in Victoria and Queensland the steel is inspected before the concrete goes in.
The same two words cover very different jobs. A path or a patio pad is one. A slab under a shed or a garage is another, and a house slab is a third. Whether a particular path or small pad needs a permit is a question for your council, and the answer varies by state, so ask. This post does not claim the code does or does not apply to a path.
What it does use is Part 4.2 of the national building code’s Housing Provisions, which covers footings, slabs and associated elements. That is the reference point for a slab under a building. One edition point, stated once: on 22 August 2026 the 2025 edition applies in Victoria, Western Australia and the ACT, and the 2022 edition applies elsewhere. New South Wales, Queensland, South Australia and Tasmania adopt the 2025 edition on 1 May 2027, so it is not yet adopted there (Tasmania also had a temporary adoption from 1 May to 4 June 2026, which has ended). The Part 4.2 words used in this post are the same in both editions.
There is a fair point on the other side. A small pad is a sensible do-it-yourself job, and nothing here says otherwise.
Search for how thick a slab should be and you will find guides that disagree. Published figures for a similar shed or garage slab run from 75 to 100, 125 or 150 mm. Public discussion offers “100 mm is the standard”, “go to 125 or 150 for a garage” and “mesh matters more than thickness”. Each has some truth in it, and none is a rule that fits every slab.
The code’s route is design-based. It lets you use the Housing Provisions only where the site is a Class A, S or M site (the ground classes in AS 2870), the slab is not more than 18 m long or wide, and the building has no more than two trafficable floors, among other conditions. Otherwise the slab is designed to AS 2870, AS 3600 or by an engineer (clause H1D4). So outside those limits the thickness you are given is an output of that design, not an input you can look up.
The written clauses of Part 4.2 give no general minimum thickness for a slab. They do give some specific numbers: 85 mm is allowed in parts of Western Australia around Perth on extremely stable sands, where a professional engineer specifies it, and fireplace pads are 150 mm for a single storey and 200 mm for two. The slab details sit in drawings. Figure 4.2.16, for footing slabs on Class A sites, is dimensioned at 100 mm for the slab, and its note allows 85 mm in the stable-sands case above, so 100 mm is a drawn figure for that case, not a rule for every slab.
What thickness does change, and plainly, is the volume. Take an invented slab of 4 m by 3 m. At 100 mm it is 1.2 cubic metres of concrete, at 125 mm it is 1.5, and at 150 mm it is 1.8. That is 25 per cent and 50 per cent more concrete than the thinnest option. This is our own arithmetic. This post does not give a price: no code or regulator publishes one, and a number with no scope behind it would mislead.
Reinforcement is where the code gets specific. Cover is the depth of concrete between the steel and the nearest surface, and it protects the steel. The Part 4.2 numbers, in the same words in both editions, are these:
| Line | What the code says | What you can look at before the pour |
|---|---|---|
| Steel | Welded wire fabric (mesh), trench mesh or bars, made to AS 2870 | Whether it is mesh, trench mesh or bars, and where it sits |
| Cover | 40 mm to unprotected ground; 30 mm to a membrane in contact with the ground; 20 mm to an internal surface; 40 mm to external exposure | A gap under and around the steel, not steel lying on the ground |
| Support | Fixed firmly and supported by bar chairs (wire, concrete or plastic) at not more than 800 mm centres for steel fabric | Chairs in rows, with the mesh sitting on them |
| Steel condition | Free of loose rust, mud, paints and oils | Clean steel, not caked in mud |
| Membrane | 0.2 mm polyethylene under a house slab and under a garage or similar slab continuous with it, laps not less than 200 mm, taped or sleeved at penetrations | Film laid flat with overlaps, no tears |
| Tiled floors | Where brittle coverings such as ceramic tiles cover more than 16 m², one of four measures: SL92 or equivalent mesh throughout the area, mesh top and bottom, a bedding system chosen for expected movement, or a wait of at least 3 months | A decision made before the tiler arrives |
Cover differs with what the steel faces, which is why there are four numbers and not one. The table is a reading of the clauses, not a substitute for the drawings.
Queensland’s building regulator makes a similar point for paths and driveways in guidance last reviewed in February 2022. Reinforcement is generally installed in the top half of the slab with a minimum of 30 mm cover, on chairs, and not dropped in or driven over by the truck. That guidance is about paths and driveways, so it is not a rule for house slabs.
Concrete does not set like paint dries. It gains strength by a chemical reaction that needs moisture and time, and the code puts numbers on both.
The concrete is specified as N20: a 28-day strength of not less than 20 MPa, a maximum nominal aggregate size of 20 mm and a nominal slump of 100 mm. Water must not be added to the mix to push the slump higher than the specified figure. A note in the code adds that the concrete should be discharged within one and a half hours of initial mixing unless a retarder is specified.
After the pour, the slab surfaces, including the edges, are moist cured for 7 days. Edges are finished after the vertical formwork is stripped and before curing starts. For a minimum of 7 days, no materials are stacked on the slab and no building plant is put on it, although construction of wall frames and setting out of brickwork may be undertaken during that period.
Then there is heat. The code says concrete must not be poured if the site air temperature exceeds 32 degrees Celsius, unless written instructions from a Professional Engineer are followed. That condition travels with the number.
You may also see 30 degrees quoted. That comes from Queensland’s regulator, in its guidance on paths and driveways, which says temperatures over 30 degrees or high wind may affect the concrete. The two figures do not clash. One is a code prohibition with an engineering exception, and the other is a planning warning for a different kind of slab.
One more note from the code: some chemical curing products may not suit the adhesives used for floor finishes, so if a floor is going on the slab, raise it before the pour.
Here is the part the thickness guides skip: who looks at the steel before the concrete covers it. In Victoria and Queensland, a regulation answers this. The Victorian text is the Building Regulations 2018, authorised version 030, incorporating amendments as at 1 July 2026. The Queensland text is the Building Regulation 2021, in the version effective from 14 August 2026.
| Victoria | Queensland | |
|---|---|---|
| Where it sits | Regulation 167, mandatory notification stages for a new building or an alteration | Section 44, inspection stages |
| Before the slab | (a) before placing a footing; (b) before pouring an in situ reinforced concrete member that the building surveyor has specified in the permit | For a single detached house: after excavation and before footings or slab concrete is poured; after formwork and reinforcement for the slab are placed but before the concrete is poured |
| Class 10 building or structure (not a pool) | Stages the permit specifies | The prescribed stage is completion of the building or structure, plus any stage the approval lists |
| Who decides the list | The surveyor may omit a stage that is not relevant (regulation 170), and the permit must specify the stages (regulation 171) | A council may exempt a locality or a type of structure from a stage (section 45) |
| Signing and notice | Not covered in what we read | Only a building certifier signs the slab stages (section 46). The builder must give the certifier notice at the completion of a stage (section 48) |
Two cautions. The Queensland stage for the steel applies to a single detached house, so a shed or garage may be inspected only at completion unless the approval lists more. And the Victorian stage turns on what the permit says, since the surveyor sets the list.
Other states are not covered here. If you are outside Victoria and Queensland, ask the certifier which stages are on the approval, and ask before the pour, not after.
Victoria’s Building Regulations 2018 list, in Schedule 12, a class of registered domestic builder that is limited to footings and slab work: footing systems, formwork, and reinforced or bulk concrete footing and structural elements. A separate structural landscaping class names driveways and paths, along with decks and pergolas. The sensible question is which class the person on your job holds, and whether it matches what they will be doing. Other states are not pinned in this post.
If the slab is part of a house build, the directory’s home builder category lists businesses that manage the whole job. For the slab on its own, the concrete contractor category is the place to look.
Cracks are the thing people see first, so it helps to know what a regulator expects. Western Australia’s building regulator published an industry bulletin in 2013 that the state republished in 2024. It says AS 2870 acknowledges that cracks cannot be entirely prevented, but they can be controlled by correct mesh location and adequate curing. It says the regulator generally regards cracks as faulty or unsatisfactory when they go beyond crack category 2, in the standard’s classification. The page does not say whether the bulletin is binding, so treat it as a yardstick.
Flatness has a yardstick too. The bulletin cites the 2009 edition of AS 3600 and says any point should deviate from a straight line joining any two points by no more than one 250th of the length of that line. By our arithmetic, that is 12 mm across 3 m and 8 mm across 2 m. Later editions of the standard may word it differently, so confirm with your certifier.
Queensland’s regulator lists concrete paths and driveways among its top ten complaint categories (its page was reviewed in February 2022). It names plastic shrinkage cracking, cracking at internal corners, patchy finish and ponding because the surface is not graded to disperse water. Agree what you will accept before the pour, not after. If a larger firm is running the build, the construction company category is another place to find someone who can write that tolerance into the job.
A small pad is a reasonable job to do yourself, and the guides that say so have a point. For a path or small pad, thickness tables and a good concreter’s judgement may be all you need. Whether it needs a permit or an inspection is the council’s call.
What changes when you do it yourself is time and weather: the code’s note on discharging within one and a half hours of mixing, unless a retarder is specified, is a short window to work in. A slab under a building is another matter again, because the design and inspection rules above apply.
The numbers to carry into the conversation are five: the grade (N20, with no water added to the mix), the curing (7 days moist), the wait before load (7 days), the cover (40, 30, 20 or 40 mm depending on where the surface faces) and the pour temperature (no pour over 32 degrees unless a Professional Engineer’s written instructions are followed). Thickness comes from the design or, inside the Housing Provisions limits, from the code’s drawn details, and in Victoria and Queensland the steel is looked at before the concrete goes in. Rules as at 22 August 2026; general information only, so check your state’s regulator.
Rules as at 22 August 2026.
Sources: Australian Building Codes Board, NCC 2022 Housing Provisions, Part 4.2 Footings, slabs and associated elements (https://ncc.abcb.gov.au/editions/ncc-2022/adopted/housing-provisions/4-footings-and-slabs/part-42-footings-slabs-and-associated-elements); Australian Building Codes Board, NCC 2025 Housing Provisions, Part 4.2 Footings, slabs and associated elements (https://ncc.abcb.gov.au/editions/ncc-2025/adopted/housing-provisions/4-footings-and-slabs/part-42-footings-slabs-and-associated-elements); Australian Building Codes Board, NCC 2022 Volume Two, Part H1 Structure, clause H1D4 (https://ncc.abcb.gov.au/editions/ncc-2022/adopted/volume-two/h-class-1-and-10-buildings/part-h1-structure); Australian Building Codes Board, NCC 2025 state and territory adoption information (https://ncc.abcb.gov.au/ncc-2025/ncc-2025-state-and-territory-adoption-information); Victorian Building Regulations 2018, authorised version 030, regulation 167 and Schedule 12 (https://content.legislation.vic.gov.au/sites/default/files/2026-07/18-38sra030-authorised.pdf); Queensland Building Regulation 2021, sections 44 to 48 (https://www.legislation.qld.gov.au/view/whole/html/inforce/current/sl-2021-0126); Building and Energy, Western Australia, Industry Bulletin 31 Placement, curing and finishing of residential concrete floor slabs (https://www.wa.gov.au/government/publications/industry-bulletin-31-placement-curing-and-finishing-of-residential-concrete-floor-slabs); Queensland Building and Construction Commission, Cementing your knowledge (https://www.qbcc.qld.gov.au/resources/article/cementing-your-knowledge)